When supplies are shifted to earlier cycles through pre-planning, what else is adjusted?

Prepare for the Kinaxis Certified Maestro Author Level 1 Exam with flashcards and multiple-choice questions. Each question includes hints and explanations. Enhance your skills and get ready to ace your exam!

When supplies are shifted to earlier cycles through pre-planning, the order of production is adjusted to minimize setup constraints. This adjustment is crucial because changing the timing of supplies inherently affects the workflow and scheduling within the production environment. By strategically altering the order in which products are manufactured, organizations can ensure that setups—such as machinery changes, tool adjustments, or line configurations—are managed more efficiently. This minimizes downtime and keeps the production process flowing smoothly, which is essential to meet the demands of pre-planned schedules and maintain operational efficiency.